Data Center Perhitungan Cost

From OnnoWiki
Revision as of 04:58, 3 September 2018 by Onnowpurbo (talk | contribs)
Jump to navigation Jump to search

e you wondering how much it will take to build your own data center or are you unsure if you have everything accounted for in your construction budget? Use this calculator to see what it really takes to build out a Tier 1, Tier 2, Tier 3 or Tier 4 data center. Options Data Center Tier Are You Currently Staffed 24x7x365 Number of Cabinets* ? Total kW of Redundant Power* ? Evaluation Period in Years ? % of Available Power Consumed ? Cost Per kWh in Cents ? Internet Connection in Mbps Power Density Meter

As you adjust the number of cabinets and the total available KW, this graphic will display the watts per square foot capacity of your data center and show how your design compares to industry standards. Low <80 Average 80-150 Medium 150-200 High 200+ Email My Configuration & Results Cost Summary BUILD YOUR OWN $6,885,171 VS ? Tier III COLOCATION SPACE $4,235,190 Total Construction Cost ** ENGINEERING AND PREPERATION Hide Details ∧ DESCRIPTION MATERIAL COST LABOR COST TOTAL Engineering $ - $220,725.00 $220,725.00 Permits and Approvals $ - $41,017.19 $41,017.19 Demolition & Outside Preparation $ - $41,017.19 $41,017.19 $302,759.38

POWER Hide Details ∧ DESCRIPTION MATERIAL COST LABOR COST TOTAL Utility Improvements $81,913.50 $35,548.23 $117,461.73 Main Switch Gear $441,450.00 $201,105.00 $642,555.00 Transfer Switches $318,825.00 $27,344.80 $346,169.80 UPS Systems $882,900.00 $196,200.00 $1,079,100.00 TVSS System $5,468.96 $5,468.96 $10,937.92 Generators with Enclosures $706,320.00 $142,192.94 $848,512.94 Counduit and Cabling for Generators $21,875.84 $21,875.84 $43,751.67 Data Center Lighting with HMT $22,969.63 $19,688.25 $42,657.88 Lightining Protection $8,203.44 $2,734.48 $10,937.92 Room PDU's $245,250.00 $196,200.00 $441,450.00 $3,583,534.86

ENVIRONMENTAL CONTROLS Hide Details ∧ DESCRIPTION MATERIAL COST LABOR COST TOTAL HVAC $304,110.00 $218,758.36 $522,868.36 Raised Floor $42,657.88 $65,627.51 $108,285.39 Condesate Drains $4,375.17 $4,375.17 $8,750.33 Leak Detection $13,125.50 $2,625.10 $15,750.60 Intergen Fire Suppresion $92,704.50 $32,813.75 $125,518.25 $781,172.93

SECURITY AND MONITORING Hide Details ∧ DESCRIPTION MATERIAL COST LABOR COST TOTAL Facility Management System $32,813.75 $5,468.96 $38,282.71 CCTV System $16,406.88 $2,734.48 $19,141.36 Building Access system $16,186.50 $2,734.48 $18,920.98 $76,345.05

NEWORK Hide Details ∧ DESCRIPTION MATERIAL COST LABOR COST TOTAL Core Network Equipment $ - $161,865.00 $161,865.00 $161,865.00

The total construction costs and the category breakdowns are based on Expedient’s experiences from the 9 data centers that they have brought online.

DATA CENTER: TOTAL COST OF OWNERSHIP Hide Details ∧ BUILD YOUR OWN Tier III COLOCATION SPACE Construction Cost $4,905,000.00 $ - Floor Space $20,000.00 $1,713,600.00 Electricity $1,132,185.60 $2,377,589.76 Electrical Maintenance $260,021.40 $ - HVAC Maintenanance $38,926.08 $ - Other Systems Maintenance $20,238.29 $ - 24x7x365 Staff $240,000.00 $ - Redundant Internet Circuits $268,800.00 $144,000.00



Referensi